This item is only available for download by members of the University of Illinois community. Students, faculty, and staff at the U of I may log in with your NetID and password to view the item. If you are trying to access an Illinois-restricted dissertation or thesis, you can request a copy through your library's Inter-Library Loan office or purchase a copy directly from ProQuest.
Permalink
https://hdl.handle.net/2142/20663
Description
Title
The relationship between alternative project approaches, integration, and performance
Author(s)
Pocock, James Bryant
Issue Date
1996
Department of Study
Civil and Environmental Engineering
Discipline
Civil Engineering
Degree Granting Institution
University of Illinois at Urbana-Champaign
Degree Name
Ph.D.
Degree Level
Dissertation
Keyword(s)
Business Administration, Management
Economics, Commerce-Business
Engineering, Civil
Language
eng
Abstract
This work compares the performance of traditional design-bid-build projects with alternative approaches. It verifies that partnered, design-build, and combination projects offer significant advantages in cost growth, schedule growth, modifications, and design deficiencies.
"Next, a method is developed for measuring ""degree of interaction"" (DOI) as an approximation of project integration. This method is used to show that DOI has a direct impact on project performance. Finally, DOI score is used to predict future project performance."
In comparing 209 completed military construction projects, partnered projects had the least average schedule growth, design-build projects had the least average cost growth and design deficiencies, and combination projects averaged the fewest modifications. Traditional projects had the worst average schedule growth, modifications, and design deficiencies. The significance of these differences is confirmed with t-tests.
Degree of interaction scores were calculated for 38 projects from this group of 209, representing each category. The alternative projects have significantly higher average DOI scores than traditional projects.
Scatter plots comparing DOI and project performance show a clear relationship between the two. As DOI scores rise, project performance quickly improves and becomes more consistent. Regression analysis shows a modest but significant correlation between DOI and project performance, including user satisfaction. Beyond a certain DOI score (approximately 0.4), performance tends to level off. Achieving this score takes only a modest increase in interaction. Threshold analysis separates the projects into those with DOI scores above and below 0.4. Performance is significantly better for projects with higher DOI in all areas except design deficiencies. Interaction occurring early in the project is also shown to have a positive impact on project performance.
Finally, these results are combined with statistical analysis to predict future project performance based on DOI scores. The probability of improved average performance for future projects with DOI $>$ 0.4 ranges from 80% to 99% depending on the performance indicator. A hypothetical project with a $5 million budget, 365 day duration, and a DOI score over 0.4, should save, on average, \$119,500 in cost growth, 71 days in schedule growth, 21 fewer modifications, and 7 fewer design deficiencies, over a comparable project with DOI $<$ 0.4.
Use this login method if you
don't
have an
@illinois.edu
email address.
(Oops, I do have one)
IDEALS migrated to a new platform on June 23, 2022. If you created
your account prior to this date, you will have to reset your password
using the forgot-password link below.